POLYMER PRODUCTION LLP

Created on:

September 13, 2012

Place of project implementation: Special Economic Zone National Industrial Petrochemical Technopark.

Participants:

United Chemical Company LLP — 99,68%

JSC MC SEZ Chemical Park Taraz 0,32%

Terms of the project implementation: 2012—2015.

Official website: www.polymerproduction.kz

First Head:

Chairman of the Board — Kairat Bulatovich Bimagambetov

Polymer Production LLP is a member of Samruk-Kazyna National Welfare Fund JSC group of companies, being an affiliate of United Chemical Company LLP.

At this time, Polymer Production LLP has implemented Investment Project Production of polymer products in Atyrau region, production is being carried out (biaxially oriented polypropylene film, polyethylene film and polypropylene bags).

This Project is included in State Program for Forced Industrial and Innovative Development of the Republic of Kazakhstan for 2010-2014, approved by Decree of the President of the Republic of Kazakhstan № 958 dated the 19th of March 2010; The program for development of chemical industry of the Republic of Kazakhstan for 2010-2014, approved by Decree of the Government of the Republic of Kazakhstan № 1001 dated the 30th of September 2010.

 

Current tasks:

Providing industrial enterprises with high-quality, technological and health-friendly products.

JSK MC “SEZ CHEMICAL PARK TARAZ”

Created on:

November 13, 2012

Place of project implementation: Special Economic Zone Chemical Park Taraz

Participants:
– United Chemical Company LLP — 18,5%
– Ministry of Industry and Infrastructure Development of RoK – 81,5%

Duration: until 2037

Official website: www.seztaraz.kz

First Head: Chairman of the Board — Anasov Dosan Temirtasovich

The aim of this project was to create attractive conditions for attracting direct investments into import-substituting and export-oriented, high-tech and competitive chemical production.

In addition, the project aims to develop and support the chemical industry, the production of high value-added chemical products and products based on them by engaging the world’s leading companies in this industry. 

Current tasks:

— was transferred to Real Estate Fund Samruk-Kazyna JSC for trust management. — 6 participants are registered, planning to carry out their activity on SEZ territory.

CHEM-Plus LLP

Created on:

7th of December 2012

 Location of the project:

Special Economic Zone Chemical Park Taraz

Participants:

– United Chemical Company LLP – 99.92%

– Samruk Kazyna Invest LLP – 0.08%

Terms of project implementation: 2012-2015

Official website:

www.chemplus.kz

First Head:

Chairman of the Board — Karazhigitov Askarbek Raisovich

The main purpose of CHEM-plus LLP is to organize industrial production of glyphosphate, caustic soda, trichlorist phosphorus and calcium chloride in the Republic of Kazakhstan.

Current tasks:

— implementation of investment projects to establish and develop competitive high value-added chemical production facilities;

— attracting investment in construction and integrated development of chemical industries;

— training and retraining of specialists for chemical productions in accordance with international standards; 4) attraction of advanced experience in management and organization of sustainable activities of chemical productions to the chemical industry of Kazakhstan.

«SSAP» LLP

Established in 2009

Place of project implementation:

Stepnogorsk, Akmola region, industrial zone 6

Participants:

– United Chemical Company LLP – 90.11%

– NAC Kazatomprom JSC – 9.89%

Project implementation time: 2010-2015

Project implementation time: 2010-2015.

Official website: http://ssap.kz/

First Head:

Chairman of the Board — Adilhan Abdrakhmanovich Umerbaev

In 2009 United Chemical Company LLP became a member of JV SKZ Kazatomprom LLP. The funds were used for reconstruction of the sulfuric acid plant with the capacity of 180 thousand tons to provide Kazatomprom’s uranium mining enterprises with sulfuric acid. In October, 2015, the reconstruction of the sulfuric acid plant with a capacity of 180 thousand tons per year was completed and the plant was put into operation. The existing production facilities were reconstructed, as well as new facilities (molten sulphur warehouse with a pumping unit, absorption unit, sulphuric acid pump warehouse, diesel fuel warehouse, railway trestle) were constructed to ensure production of high quality product. The installed equipment and technology meet international standards.

Current tasks:

— provision of sulfuric acid to uranium mining enterprises of JSC NAK Kazatomprom. Solving the problems of sulfur processing that have a negative impact on the environmental situation in the Caspian region (currently, Tengizchevroil LLP (“TCO”) has about 8 million tons of sulfur on its sulfur maps);

— development of the chemical industry in the northern regions of Kazakhstan through sulphur processing using modern technologies.

Kazakhstan Petrochemical Industries Inc. LLP  (KPI Inc. LLP)

Created in:

2008

Project implementation location: Special Economic Zone National Industrial Petrochemical Technopark of Atyrau region 

Participants:

—  United Chemical Company LLP — 99%

— Almex Plus Firm LLP — 1%

Project start date: 2021

Official website: www.kpi.kz

First Head:

Chairman of the Board — Tiesov Daniyar Swinshlikovich

Kazakhstan Petrochemical Industries Inc. LLP was developed within the framework of the “Program of Petrochemical Industry Development of the Republic of Kazakhstan for 2008-2013”, approved by the Resolution of the Government of the Republic of Kazakhstan dated December 29, 2007 No. 1352, in order to use the existing large volumes of gas from Tengiz and Kashagan fields as the initial raw material for the gas-chemical complex for production of expensive petrochemical products for further sale in the domestic and export markets. The project is included into the State program on accelerated industrial-economic development of the Republic of Kazakhstan for 2010-2014, approved by the Decree of the President of the Republic of Kazakhstan dated March 19, 2010 No. 958.

Current tasks:

— Construction of the first integrated gas-chemical complex in Atyrau region;

— Operation of the Complex, including production and sale of industrial products manufactured by the Complex;

— Implementation of measures necessary for and related to engineering, design, and construction of the Complex, but not limited to the performance of customer functions and technical supervision under contracts for design, procurement and construction of the Project, the Complex and all other related contracts; 

— Implementation of measures related to attraction of financing for the Project and the Complex implementation;

— Implementation of measures on production and sale of industrial products manufactured by the Complex, including all products of gas processing and petrochemistry.

Karabatan Utility Solutions LLP (KUS LLP)

 Created in:

2014

Place of project implementation: Special Economic Zone National Industrial Petrochemical Technopark of Atyrau region

Participants:

– United Chemical Company LLP – 99,999999%

– Polymer Production LLP – 0,000001%

Terms of project implementation: 2014 – 2018

Official website: www.kus.com.kz

First Head: Chairman of the Board – Mami Erlan Erkeshevich

Karabatan Utility Solutions LLP was established in 2014 by the decision of the general meeting of the company participants dated August 20, 2014.

Current tasks:

 – construction and operation of complexes, production facilities and plants for hydrocarbon processing;

– design, construction and commissioning of infrastructure facilities within the Special Economic Zone;   

– production of electric and (or) heat energy for own needs and (or) implementation;         

– operation of production, administrative and infrastructure facilities within the framework of investment projects;        

– production and sale of industrial products manufactured within the framework  of investment projects implementation;         

– implementation of measures necessary for and related to engineering, design, and construction of production, administrative, and infrastructure facilities within the framework of investment projects implementation.

KLPE LLP

Created in:

2017

Place of project implementation: Special Economic Zone National Industrial Petrochemical Technopark of Atyrau region

Participants:

— United Chemical Company LLP — 99,90409%

— Polymer Production LLP — 0,09591%

Official website: www.klpe.kz

First Head:

Chairman of the Board — Alzhan Imashev.

 

Construction of an integrated gas chemical complex in Atyrau region. With the assistance of National Welfare Fund Sampuk – Kazyna JSC, a strategic partner — LG Chem, Ltd. was involved. Currently LG Chem, Ltd. is a member of KLPE LLP (50%), and United Chemical Company LLP (50%). 

Current tasks:

— design, construction and operation of the second phase of the world-class gas chemical complex in Atyrau region.       

— production and sale of polyethylene and other industrial products, including all products of gas processing and petrochemistry.

MC “SEZ NATIONAL INDUSTRIAL PETROCHEMICAL TECHNOPARK” JSC

Created: November 19, 2007

Place of project implementation: Atyrau region

Participants:

— United Chemical Company LLP — 13.39%

— Ministry of Economy of the Republic of Kazakhstan — 86.61%

Duration: until 2032

Official website: www.nipt.kz

First Head:

Chairman of the Board — Aslan Daurenbekovich Kalabaev

 

The purpose of creating the SEZ was to develop and implement breakthrough investment projects to create and develop world-class petrochemical production facilities for deep processing of hydrocarbons and production of a wide range of competitive high value-added petrochemical products.